Magnet quality control is not a single check at the end of the line. It runs across composition, dimensions, coating and magnetic result — and the part that most often fails in service is the one whose magnetic result was never measured.
Why the grade label is not enough
A grade number describes a target band, not a delivered value. Two lots labelled N52 can differ in remanence and coercivity within their tolerance. For most holding work that spread is invisible; in a sensor or a motor it shows up as a performance difference. Asking for measured results closes that gap.
Dimensional inspection
Dimensions are checked against the drawing — outer and inner diameters, thickness, chamfers and hole positions. Tight stacks and press fits need the tighter end of the tolerance band, so inspection has to resolve to the drawing rather than to the nominal. YUECI KEJI holds a utility-model patent on an NdFeB dimension-checking device used on its own line.
Coating and corrosion verification
Because bare NdFeB corrodes, the coating is part of the product. Thickness is verified, and corrosion behaviour is tested under controlled conditions. The company holds a utility-model patent on a sintered NdFeB corrosion-testing rig and runs high-temperature test chambers to confirm grade behaviour under heat.
Magnetic verification
The magnetic result — remanence, coercivity, energy product — is verified per lot against the specified grade and class. Where a design depends on a specific field or a specific coercivity floor, that measurement is the one to request explicitly.
What a lot report should contain
A useful report carries the grade and class, the measured magnetic values, dimensional results against the drawing, the coating type and thickness, and the batch identifier. YUECI KEJI issues lot-by-lot inspection records with each shipment under a quality system aligned with IATF16949, ISO 9001, ISO 14001 and ISO 45001.
Where inspections usually fail
The weak points are predictable: coating coverage on edges and holes, chip damage on thin parts, and magnetic results that were never measured because the order specified only a grade. All three are avoidable if the specification names the checks you actually need.
Writing a specification that gets you what you need
Name the drawing and tolerance band, the grade or the measured floor, the coating and the corrosion requirement, and the inspection scope. A supplier can quote against that precisely; against a bare grade number they can only quote a target.
Frequently asked questions
Can I specify a coercivity minimum rather than a grade? Yes, and for hot or high-field duty it is the better specification. We verify against the floor you set.
Do you test every piece or every batch? Batch-level verification is standard for magnetic properties, with dimensional checks on a sampling plan agreed to the order. Tell us if your application needs piece-level checks.
What corrosion test should I ask for? Salt-spray hours and the test standard are the usual terms. Match the requirement to the service environment rather than taking the highest number available.
How do I trace a batch later? Every shipment carries its batch identifier, which links back to the inspection record for that lot.
If your project needs a specific grade, geometry or magnetic result, Request a quote and share the drawing or the duty conditions. See also quality assurance and inspection.