A quoted schedule for a magnet order is not a single number pulled from a table. It is the sum of several queues, each of which can be the long one on a given order, and the art of planning a magnet project is knowing which queue is binding. Here is what is actually in the schedule.
Material availability
For a stock grade, material is usually available. For a specific grade with a heavy rare-earth content, or for a large order that commits a significant quantity of feedstock, material availability can be the binding constraint, particularly when the rare-earth market is moving. This is the queue that is least under any supplier's control, and it is why a responsible quotation states its assumptions.
Tooling
A custom pressed part needs a die, and a multipole part needs a magnetizing fixture. Both are machined, proven and adjusted, and both can take a meaningful fraction of the total schedule on a new part. This is the queue that makes the first order of a new part longer than every order after it, and it is why a program's second order is usually much faster than its first.
Pressing and sintering
Pressing is fast once the tool exists, but sintering runs in batches through a furnace, and the batch has to be full to be efficient. A small order may wait for a batch; a large order may need several. Grinding follows, with its own setup and queue, and the tighter the tolerance the longer the grinding stage takes.
Coating and magnetizing
Coating is a batch process with its own queue, and multi-layer coatings such as nickel-copper-nickel take longer than a single layer. Magnetizing is fast per part but needs the fixture and the pulse equipment, and multipole parts need a fixture verification step before the run.
Inspection and documentation
Final inspection, packing and documentation are usually a small part of the schedule, but they are the part that cannot be compressed without cutting corners, and they are the part that matters most when the parts arrive. Export documentation, where the grade requires it, adds time that is set by the licensing process rather than by the factory.
How the stages add up
A stock shape in a common grade, with standard tolerance and coating, is a short schedule because there is no tooling and the material is on hand. A custom pressed part in a standard grade adds tooling. A multipole part adds a fixture and its verification. A tight tolerance adds grinding time. A special coating adds a process step. A grade needing export documentation adds licensing. Each is manageable; the surprise comes when several arrive together and nobody said so.
How to plan around it
Ask for the schedule broken into stages rather than as a single number, and ask which stage is binding on your order. Start the sample stage early, because sample approval is a gate that production waits behind. Where a program is coming, commit to a volume plan so tooling can be amortized and material reserved. And where a date is genuinely critical, say so at quotation stage, because a schedule that is impossible can usually be made possible by changing the tolerance, the coating or the grade, but only if the constraint is known in time.
Frequently asked questions
Why is the first order slower than the re-orders?Tooling. The die and the magnetizing fixture are built and proven once, and every order after that starts from an existing tool.
What compresses a schedule most reliably?Removing a constraint rather than pushing one: a standard geometry instead of a custom profile, a standard tolerance instead of a tight one, or a stock grade instead of a special one.
Can samples be expedited?Often, because they skip the production queues, but they still need tooling for a custom part, and tooling is not usually the expeditable stage.
How is the schedule tracked?Against your order, with stage-by-stage status, and with any slip communicated as it happens rather than at the shipping date.
Planning a program? Send the specification and the target date and we will tell you which stage is binding and what it would take to move it.