Every serious magnet project passes through a sample stage, and the way it is handled determines whether the production run matches what the buyer expected. Sample approval is not a formality and it is not a purchase; it is the act of agreeing, in writing, on the definition that production will be built to.
What the supplier sends
A sample package should contain more than parts. It should carry the measured dimensions, the flux or surface field values, the coating type and thickness, and where relevant the magnetic values from a hysteresisgraph measurement. It should reference the drawing revision the parts were built to. If a sample arrives with no data, the data is the first thing to ask for, because a part you have measured and a part the supplier has measured are two different levels of confidence.
What to check on receipt
- Dimensions: measure the functional dimensions yourself rather than relying on the report, at least on the first sample.
- Magnetic values: compare the reported flux or field against what your application needs, not against what looks impressive.
- Fit and function: assemble the sample into the real assembly, or into a fixture that represents it.
- Environment: if the application runs hot, wet or vibrating, run a short test rather than assuming.
- Appearance and edges: check the chip and crack envelope and the coating coverage.
How to give usable feedback
The most useful feedback is measured, not subjective. "The magnet is too weak" starts an argument; "the measured flux is 15 percent below the reported value and the sensor misses triggers at a 3 mm gap" starts a fix. Where a change is needed, state the change against the drawing revision, so both sides are looking at the same document. Where the sample is acceptable, say so in writing and say what was checked.
What approval locks
Approval against a drawing revision freezes the definition: the geometry, the grade, the coating, the magnetization pattern, the tolerance and the inspection level. Production is then built to that definition, and deviations require a change request. This is the step that makes a lot record meaningful, because the record compares production against an approved baseline rather than against an intention.
When to re-approve
Four changes require re-approval, and all of them happen in normal production. A change of feedstock lot, where the grade is the same but the supplier of the powder has changed. A change of tooling, after a die repair or replacement. A change of coating, including a change of plating line or thickness. And a change of process, such as a new sintering furnace or grinding machine. A supplier who tells you about these changes is a supplier you can build a program with.
The paperwork habit
Keep the approved sample, the approval record and the lot records together, against the part number. When a re-order arrives two years later, that file is what lets the supplier reproduce the original rather than approximate it. It is also what turns a field complaint into a measurable comparison instead of a debate.
Frequently asked questions
How long should approval take?Days, if the measurement is straightforward. Weeks, if the application needs an environment test. What matters is that the approval is written, not how fast it is.
Can production start before approval?Material can be prepared, but pressing to a custom tool should not start before approval, because a revision after pressing is a new tooling conversation.
What if the sample is perfect but the drawing is wrong?Fix the drawing first, then re-approve. A perfect sample of the wrong part is still the wrong part.
Do you supply the measurement data with samples?Yes. Dimensions, flux or field, coating thickness and, where relevant, magnetic values, all against the drawing revision.